Clear Fork Interceptor Project

Clear Fork Interceptor - Exhibit A

Clear Fork Interceptor Project:

  1. Schedule:  Project Started on 1/3/2023 and is scheduled for substantial completion 8/1/2023
  2. Mobilization and Preparation of Right-of-Way: January 2023
  3. Tunnel Installation: February-March 2023
  4. Gravity Sewer Installation: March-June 2023
  5. Old Tunnel Lift Station Site Work:  May-July 2023
  6. Closeout and Cleanup: August 2023

Clear Fork Interceptor - Exhibit A