Clear Fork Interceptor Project
Clear Fork Interceptor Project:
- Schedule: Project Started on 1/3/2023 and is scheduled for substantial completion 8/1/2023
- Mobilization and Preparation of Right-of-Way: January 2023
- Tunnel Installation: February-March 2023
- Gravity Sewer Installation: March-June 2023
- Old Tunnel Lift Station Site Work: May-July 2023
- Closeout and Cleanup: August 2023
Clear Fork Interceptor - Exhibit A
If you have any questions regarding this project please contact Public Works, at (817)441-7016.